Road Closure Schedule thru 7/12/21
1-Jul
Close Intersection of Maple and Walnut
Close Intersection of Maple and Oak - 1/2 day
2-Jul
Close Intersection of Maple and Walnut
Second crew on lower Walnut pipe crossing - DW 8 to existing CB
6-Jul
Close Intersection of Walnut and Lawrence - Drywells
Possible 12" sewer pipe repair - Lower Walnut
7-Jul
Close Intersection of Walnut and Lawrence - Drywells
Begin Sewer Lateral Cleanout installation
- Local traffic only
8-Jul
Sewer lateral cleanout installation crew
- Local traffic only
Sewer lateral replacement crew
- Local traffic only
9-Jul
Close intersection of Maple and Walnut - DW 5 to CB 2
Sewer lateral crew - Local traffic only
12-Jul
Close upper Walnut pipe crossing - DW 13 to DW 14
Sewer lateral crew - Local traffic only