Dix Avenue Pavement Preservation Project
Schedule - Weather Permitting
Monday June 14th to Friday June 18th
Waterline
o Perform Bike Path Tie-In. Completion of contract water line work.
Drainage
o Install drainage north side of Dix Avenue between Ridge Street and Sagamore Street.
Sanitary
o Begin new sanitary between Prospect Street and Sierra Street.
Highway
o Continue sidewalk and curb box out from Byrne Street to Platt Street.
o Pave utility trenches.
o Pave driveway aprons between Ridge Street and Walnut Street.
Monday June 21st to Friday June 25th
Drainage
o Install drainage north side of Dix Avenue between Sagamore Street and head east towards Platt Street.
Sanitary
o Complete new sanitary between Prospect Street and Sierra Street with Sanitary Laterals tied in.
Highway
o Continue sidewalk and curb box out from Byrne Street to Platt Street.
o Resume placing curb and sidewalk on south side between Sagamore Street and Platt Street.
o Begin curb and sidewalk box out between Ridge Street and Sagamore Street on the north side of Dix Avenue
Tuesday June 28th to Friday July 2nd
Drainage
o Install drainage north side of Dix Avenue between Sagamore Street and head east towards Platt Street.
Highway
o Complete sidewalk and curb box out from Byrne Street to Platt Street.
o Complete south side curb and sidewalk. Tentatively begin north side curb and sidewalk placement between Ridge Street and Sagamore Street.
o Complete curb and sidewalk box out between Ridge Street and Sagamore Street on the north side of Dix Avenue
Anticipate Dix Avenue Eastbound Travel Lane Closed from Ridge to Prospect Street with Detour in Place.
All through traffic between Ridge Street and Walnut Street closed. Local traffic and patrons allowed.